Project Schedule/news
Phase IV-C Utility Improvements Project
City of Fort Myers
Road Watch
Update
Engineering Division of Public Works
July
11, 2008 to July 25, 2008
Phase
IV-C Utility Improvements Project
Area C-1: LaPalma,
Winkler
Sanitary
and storm sewer installation in progress on LaPalma and
Winkler.
Sections
of LaPalma and Winkler may be closed to thru traffic during working
hours.
Area C-2 (Additive): Jefferson, Winkler,
Princeton
Final surface course paving
in progress on Princeton. Raised intersection installation in
progress at Jefferson and Princeton.
Sections
of Princeton may be temporarily closed during working
hours.
Area
C-5: Shadow Lane
No anticipated closures at
this time.
Area C-2
and C-4: Jefferson Ave
Sections
of Jefferson Avenue may be closed to thru traffic during working
hours.
Please keep in mind this phasing schedule is a tentative schedule
developed for planning purposes. This schedule may vary depending
on the actual condition of underground utilities, delivery of
materials and equipment and weather conditions. Unforeseen issues
may require extra time during construction.
Once construction starts, the contractor will generally have 90
days on each block to produce a dust-free drivable surface. A
dust-free drivable surface consists of a limerock base with a
weather sealer.
|